Implementation

 

Laying of setts

Sett pavement upon bed

A: sett
Ar: sand bed
CN: levelling layer
BE: structural base
G: geotextile layer
E: subgrade


Setts may be placed upon a previously compacted sand bed or upon mortar.

The pointinf can be realised with sand or with pointing material specific for this end:

The sand pointing is done by sweeping the granular material over the sett surface until it penetrates sufficiently. The excess sand should also be removed by sweeping.

Once the sand pointing is completed, vibrating compaction of the pavement must be done using vibrating plates coated with neoprene or vibrating roller compractors.

The pointing with concrete adhesive can be used throughout the height of bonding joints or by sand pointing at the bottom layer and the top layer with this type of adhesive.
Laying of sets on sand bed
Vibration of the sett
Pointing of sets with concrete adhesive
 
 










FCTGG © 2012 |  Centro Tecnológico del Granito Ribeira, S/N, Torneiros. 36410 | O Porriño (Pontevedra)
986 348 964     info@fctgranito.es Área privada   mapa web | cómo llegar | descargas | enlaces
página promocionada por:

© Ideaspropias Publicidad